Consider a cancer hospital with 20 ORs allocated Monday to Friday from 7 am to 5 pm. Staff scheduling is also from 7 am to 5 pm, such that nursing overtime begins at 5 pm and anesthesiologists receive incentive (bonus) payment for work after 5 pm. All ORs are full to at least 3 pm every day, but because of costs versus reimbursement the workday has not been extended past 5 pm (8,9). OR #1 has two cases realistically scheduled 7 am to 10:30 am for surgeon A and 11:00 am to 3:15 pm for surgeon B. OR #2 has one long head-and-neck case with reconstruction scheduled to end at 8 pm. At 7 am, the anesthesiologist assigned to ORs #1 and #2 is standing outside of the rooms. The Certified Registered Nurse Anesthetist (CRNA) from OR #1 is wheeling her first patient down the hall. The CRNA for OR #2 is nowhere to be found, and the anesthesiologist is not sure of the patients status either. Results of our companion article (1) are that, without prompting from a command display, many anesthesiologists would get the case started in OR #1, hoping that by then the situation in OR #2 would be addressed. Doing so increases the clinical work per unit time of the ORs to which the anesthesiologist is assigned at each moment the anesthesiologist is present. However, the staffing is planned to 5 pm in OR #1. There will be no overutilized time in OR #1 regardless of whether the case starts at 7 am or 7:15 am. The anesthesiologist should first determine what is happening to OR #2, because every minute waiting to start OR #2 is an additional minute of overutilized OR time and higher costs (2,3). The reduction in costs is a higher priority than patient and surgeon waiting at the hospital because, otherwise, the ORs would have been allocated and staffing would have been planned beyond 5 pm (3,10). In addition, a scheduled delay would have been planned between the first and second case (surgeons) in OR #1, so that if the first case finishes unexpectedly late the second case would still start on time (2,11,12). From the experimental design of our companion article (1), we cannot rule out the possibility that the clinicians were not making managerial decisions to increase the clinical work in each OR at each moment, but rather neglecting long- and short-term institutional goals in lieu of decisions that they expected would avoid confrontation. The reason is that the experiments considered decision-making on the day of elective surgery, when decisions to reduce overutilized OR time can conflict with reducing surgeon waiting. In the current article, we take advantage of two unusual situations at a hospital to differentiate between explanations. For Study #1, we review anesthesiologists managerial decisions when they are performing anesthesia outside of ORs and making independent decisions one case (patient) at a time. The importance of the non-OR setting is that although previous studies of status displays for managerial decision-making involved individual ORs (Table 2 of Ref. 1), activity in one OR often indirectly affects activity in another OR (e.g., based on calls from the OR control desk). For Study #2, we investigate decision-making on weekends, when anesthesiologists decisions that increase their personal clinical work has the effect of increasing surgeons waiting.
METHODS
Study #1: One List of Patients with Pagers The working day before a patients procedure, an educational e-mail was sent to the anesthesiologist explaining that he or she would be sent a text page (i.e., active status display) notifying him or her when each patient arrives at the preanesthesia evaluation clinic. The e-mail stated: "If your preceding case finishes early, you can page the patient and make arrangements to start the case early ... If you are running behind, you can notify your patient ..." The patients or parents of a patient were given a pager upon arrival at the preanesthesia evaluation clinic on the day of the anesthetic. Each anesthesiologist was assigned one sequential list of cases and was paired with one CRNA, resident physician, or student registered nurse anesthetists (SRNA) (i.e., anesthesiologists were not medically directing multiple sites). Consequently, clinicians reasonably had complete knowledge of the information required to make the decision to page patients. The OR control desk was uninvolved. The use of pages was started at the hospital November 1, 2005. Data were collected through the end of January 2006. The dates and times of uses of the pagers were obtained from hospital telecommunications. The scheduled and actual start and end times of the anesthetics were obtained from the departments billing data. The data for observational Study #1 were these lists of dates and times. Our explanation for clinicians decision-making would be supported by two findings. First, routine use of the pagers would be expected for cases that started early, because such use would increase the anesthesia providers work per unit time. Comparisons were made of 1) times that pagers were used and 2) times that cases were scheduled to start. Second, few pages would be made to patients (parents) to reduce the anesthesia providers hours worked late. When anesthesia providers who were assigned to locations outside of ORs finished their list of patients, they had completed their daily clinical assignment. Relief from ORs was rarely, if ever, available, meaning those providers finished their list. Because cases were not scheduled into overutilized time, the overutilized time occurred when cases were taking longer than scheduled. If pages were sent frequently, but rarely on days with overutilized anesthesia time, then the decision to page was unlikely to have been made based on reducing expected hours of overutilized anesthesia time. For each patient receiving a pager, the time of the actual end of the workday was known. Analysis was made of page/no-page versus overutilized anesthesia time/no overutilized anesthesia time.
Study #2: Impact of Education on Decisions Involving Multiple ORs The OR allocation planned for nights and weekends was three ORs (15,16). Based on that staffing plan, OR nursing and the anesthesia departments scheduled its staff (i.e., determined the individuals who would work each shift on each day) (17). The shifts worked at the hospital were nights 7:00 pm to 7:00 am the next morning and weekend days 7:00 am to 7:00 pm. All cases started during these periods were sufficiently urgent that the surgeons judgment was that they could not wait for the next scheduled workday. CRNAs, resident physicians, and SRNAs were scheduled in-house. One anesthesiologist was scheduled to work a 12-hr shift in-house to cover 2 ORs. Backup anesthesiologists were on call from home for cardiac, liver transplantation, and nonspecialty cases. Because cases were almost always finished by the next workday, there was no overutilized OR time to be created by decisions. In addition, following the American Council for Graduate Medical Educations Program Requirements for Resident Education in Anesthesiology (August 4, 2005, line 451), each anesthesiologist medically directed one or two ORs. Consequently, by definition, each decision made by an anesthesiologist that increased his or her clinical work per unit time by not calling in another anesthesiologist to run a third OR resulted in surgeons and patients waiting longer. For example, one evening an anesthesiologist working in-house made decisions to increase his/her clinical work per unit time during his shift of fixed duration, following our hypothesized explanation of clinicians managerial decisions. He allowed a second anesthesiologist to go home at midnight while a patient waited safely a few hours until one of two ongoing cases finished. The decision increased the clinical work of the anesthesiologist on call in-house (i.e., satisfied our hypothesis). The departments culture may have rewarded the anesthesiologist intangibly for personally doing so many cases. Nonetheless, the decision was made without consideration of its effect on the unobserved patient, surgeons, emergency department, surgical pathologist, postanesthesia care unit nurses, and surgical ward nurses. A purpose of the OR allocations was to permit staff scheduling decisions to be made independently by these different stakeholders. None of this would have been an issue if the heuristic of working fast had been applied only to decisions involving one OR. The ORs used on nights and weekends were those along a hallway in front of the OR control desk and the anesthesia supply room. Thus, the anesthesiologists had all of the data required to make the studied decision. The data used were, for each case, the time when the surgeon reported that he or she and the patient were available, time that the case started, and when it ended. Cases were considered to take 45 min for OR preparation and anesthesia evaluation. Sensitivity analyses were performed with other values to assure that results were unaffected. If there were zero ORs in use between when a case was submitted and started, the case was not considered to have been waiting for an OR. This assumption was reasonable, based on the authors not being aware of an anesthesiologist or charge nurse at the hospital ever deciding to run zero ORs while a case was waiting other than during a power failure, which did not occur during the studied period. This assumption will also be shown to be supported in the Results by our finding from Study #1. The consequence of the assumption is that the analysis assessed the minutes of patient and surgeon waiting while one or two ORs were in use. The training sessions started October 2005. The data were analyzed through the end of January 2006. Baseline data were January 2004 through September 2005. There were 3310 cases started during nights or weekends. The data were pooled into 2-wk periods to eliminate the effect of variation in workload by day of the week on results (e.g., as shown in Ref. 16). The intervention period was the last 8 of 54 successive 2-wk periods. No changes were made to staffing or staff scheduling during the 54 periods. The sample size within each 2-wk period was sufficient for pooling as each contained 14 nights and 4 weekend day calls. RESULTS The anesthesiologists used the pagers mostly when doing so increased their clinical work per unit time (Table 1). Each increase in the minutes starting earlier than scheduled was associated with an increase in the probability of the patient being paged (P < 0.001). Decisions on nights and weekends also were consistent with the hypothesis that clinicians used a heuristic of increasing their clinical work per unit time (Table 2). Education did not change decision-making or reduce the patients and surgeons waiting at the hospital (P = 0.75). DISCUSSION Although reducing overutilized OR time has advantages for OR nurses, housekeepers, and anesthesia providers (e.g., consistent decision-making, more predictable work hours, fewer handoffs during cases, reduced staffing costs, and less unscheduled [mandatory] overtime) (2,3), such decisions often result in increased surgeon and patient waiting. In our companion article (1), we showed that when decision-making on the day of elective surgery involves multiple ORs, decisions are often made not to reduce overutilized OR time, but potentially to increase clinical work at each moment in each OR. However, as shown by the example in the introduction, an alternative explanation could be to increase surgeons and/or patients satisfaction. The two studies of this article show that the latter explanation does not apply. Anesthesiologists managerial decisions were consistent with a heuristic of increasing their personal clinical work per unit time. In addition, education and near perfect knowledge of status were insufficient to change such decisions. Command displays (recommendations) are needed (1). As considered in the Introduction of our companion article (1), there is an excellent basis for the heuristic of increasing the clinical work per unit time of each OR. The vast majority of OR management decisions that involve single ORs (18,19), for which decisions are the same as those that reduce both overutilized OR time and expected tardiness from scheduled start times (1,2). The problem is the subsequent application of this heuristic to decisions involving multiple ORs. Study #1 alone was incomplete, because there was another explanation for the decision-making other than use of the heuristic of trying to increase clinical work per unit time. The times at which the anesthesiologists finished their scheduled lists of cases outside of ORs were generally how late the anesthesiologists worked caring for patients. Thus, the pagers could have been used when the decision to use the pager could result in the anesthesiologists finishing their clinical day earlier. Study #2 shows that the latter explanation is unlikely. During nights and weekends, the work hours were set at 12 h, and still the anesthesiologists made the same decisions. Furthermore, in the experimental study (1), decisions had nothing to do with getting home sooner. Study #2 alone was also incomplete, because surgeon and patient waiting at the studied hospital may have not changed because waiting resulted from anesthesiologists postponing decisions when they were busy caring for patients. However, that alternative explanation cannot explain the findings of our companion article (1) in which the heuristic was followed despite absence of time requirements or clinical care responsibilities (7). Furthermore, anesthesiologists may have made decisions in Study #2 based on a perception that the allocated OR time at night should have been less than the prescribed three ORs (e.g., fewer providers on-call from home having to do cases, increasing provider satisfaction). However, our companion article (1) studied weekday staffing that had been unchanged at the hospital for 9 yr.
Footnotes Accepted for publication April 16, 2007. Dr. Dexter, Section Editor for Economics, Education, and Policy, was recused from all editorial decisions related to this manuscript. FD is Director of the Division of Management Consulting of the Department of Anesthesia of the University of IA. He receives no funds personally other than his salary from the State of IA, including no travel expenses or honoraria, and has tenure with no incentive program. An abstract describing this work was presented at the Institute for Operations Research and Management Sciences Annual Meeting, Pittsburgh, PA, on November 5, 2006. REFERENCES
This article has been cited by other articles:
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|